Fenix Resources plans 10 Mtpa Weld Range Project expansion
Fenix Resources (ASX:FEX) has released the results of a scoping study on its Weld Range Iron Ore Project, outlining a strategy to expand production, reduce costs, and extend the mine’s operational life to 2042.
The study aligns with Fenix's Weld Range right-to-mine agreement with Sinosteel Midwest Corporation, part of China Baowu Steel Group, targeting an export production rate of approximately 10 million tonnes per annum.
Key findings include a ramp-up of production from 6 Mtpa in 2028 to 10 Mtpa by 2031, with life-of-mine cash costs projected at around $55.4/wmt FOB Geraldton—27% below the FY26 guidance midpoint.
The project is expected to reach an all-in breakeven price at a 61% Fe CFR index price of roughly US$67/dmt.
Financial metrics are compelling, with a pre-tax NPV10 of approximately $1.2 billion, an IRR of ~60%, a payback period of 2.6 years, cumulative pre-tax free cash flow of ~$2.5 billion, and average annual EBITDA of ~$235 million.
Infrastructure improvements include a planned 244 km private haul road, reducing port haulage distance by 20% and allowing a 70% increase in payload per truck.
The mine is expected to produce high-grade iron ore averaging 58% Fe over its life, with early-stage Beebyn ore at ~61% Fe offset by lower-grade Madoonga ore at ~56% Fe.
Total development capital is estimated at ~$521 million, largely required from 2028, giving Fenix time to assemble a funding package from operational cash flows and potential external debt.
A definitive feasibility study is underway, with completion expected in June 2026 and a final investment decision anticipated in 2028.
More from Australia
Woodside Energy cuts 500 jobs to slash costs by US$570M
NSW panel recommends 26 stricter data centre rules
Top End Energy applies to surrender permit EP 153
Neuren Pharmaceuticals upgrades full year guidance
Vicinity Centres places earnings guidance under review
Resources & Energy expands Menzies Project by 69%