Terawulf expands Muskie data campus capacity to 1 GW
- TeraWulf (NASDAQ:WULF) signed an amended electric service agreement with Kentucky Power, increasing contracted capacity at its Muskie Data Campus to 1 GW from 500 MW.
- Planned delivery of the second 500 MW phase moved ahead from 2030 to 2029, pending regulatory approvals and utility construction timelines.
- The company stated that the site development supports phased artificial intelligence and high-performance computing infrastructure.
TeraWulf (NASDAQ:WULF) secured expanded electrical capacity to accelerate development at its Muskie Data Campus.
The site, acquired in May 2026 for AI and high-performance computing initiatives, maintains its target to begin ramping the initial 500 MW phase in 2028.
Kentucky Power is actively developing a dedicated substation connected to the regional transmission network to support the massive energy load.
Following the announcement, TeraWulf's share price was up at $7.40.
Looking beyond the current 1 GW commitment, leadership continues evaluating potential expansion up to 2 GW, contingent on further utility planning and regulatory compliance.
All future construction will align directly with Governor Beshear's Executive Order on Data Center Development.
Frequently asked questions
More from United States
AbbVie revenue increases 10.3% to $17.4 billion in third quarter
Sensient Q3 revenue rockets 10.6% to $455.8 million
Cameco Q3 adjusted loss reaches CA$2 million as uranium output falls
Kite Realty Q3 loss narrows to $13.3 million as NOI grows
Largo cuts 2026 vanadium production outlook to 9,500–10,500 tonnes
nVent Q3 sales jump 44% as shares fall despite higher revenue
_1435119_640x360_2505873987511-640x360.webp&w=3840&q=75)