
Theta Gold Mines targets first gold pour in 2027
Key points
- Theta Gold Mines reported that construction of its South African gold processing plant is 81% complete ahead of a planned early 2027 production start.
- The company holds $96.2 million in cash after drawing $109.6 million from its bond facility.
- Theta Gold plans to process existing rock dumps first before transitioning into a 13.1-year underground mining operation.
Theta Gold Mines (ASX:TGM) announced that construction of its Transvaal Gold Mining Estates gold processing plant in South Africa is 81% complete as it targets its first gold pour in the March quarter of 2027.
This progress follows $84.8 million in development spending through October and the stockpiling of 110,000 tonnes of ore for plant commissioning.
The company holds $96.2 million in cash and $20.8 million in undrawn funds after completing a second drawdown on its $136.4 million Nordic bond facility on Nov. 25.
Following the announcement, the Theta Gold Mines share price was down at $0.17.
Theta Gold stated that dry commissioning is scheduled for the December quarter, with final completion in the March quarter remaining subject to regulatory approvals.
The company holds a 74% stake in the Mpumalanga province project, where a February feasibility study projected 871,000 ounces of gold recovery over a 13.1-year operating life.
Theta Gold plans to begin production using existing surface rock dumps while preparing four underground mines out of 43 historical gold sites across its holdings.
Frequently asked questions
More from Australia
Neuren Pharmaceuticals drops 10.65% after FDA trial update
Auric Mining begins 13,000-metre Union Jack drill program
Laserbond forecasts $19–$20M first-half revenue
Elk Range Mining executes US$4M Friday acquisition
3P Learning launches strategic review after $19.5M profit
Vitura Health forecasts up to 60% earnings growth in FY27
