Latrobe Magnesium completes 100% of Phase 1B installation
Key points
- Latrobe Magnesium has completed 100% of equipment installation for its Phase 1B Project and reached 78% commissioning.
- The company stated that project spending remains within its original $6.1 million budget.
- Management expects this furnace heating stage to enable first magnesium metal production by the end of 2026.
Latrobe Magnesium (ASX:LMG) completed 100% of equipment installation at its Victoria demonstration plant and advanced commissioning to 78%.
Commissioning progressed from 50% on Oct. 31, following the completion of briquetting ore trials and furnace sealing.
"Work in November has progressed at a steady and controlled pace, with commissioning work being the focus. With the furnace heat-up process now under way, we remain firmly on track to produce first magnesium metal by the end of 2026," said Latrobe Magnesium CEO Robert Stein.
The company stated that spending remains within its $6.1 million budget as staff prepare for a four-week operational campaign.
Following the announcement, the Latrobe Magnesium share price was down at $0.013.
Latrobe Magnesium is developing a patented extraction process to produce magnesium metal from brown coal ash in Victoria.
Frequently asked questions
More from Australia
NIB maintains $265M to $285M profit guidance
Mining One earns 25% interest in Infinity Mining project
Mount Hope Mining begins 2,000m gold drilling at Mt Solitary Project
WA1 Resources wins strategic status for Luni Project
Beach Energy confirms discussions to buy Santos assets
Industrial Minerals starts heritage survey on 1,700m gold target