Flagship wind farm delay blow to Victoria's green goals
Victoria's transition to renewable energy has been dealt a major blow following revelations that the state’s flagship offshore wind project, Star of the South, will not be fully operational until at least 2037.
New regulatory documents reveal the 2.2-gigawatt project is scheduled to begin construction in 2030, pending approvals, with a staged seven-year build timeline.
The delay casts severe doubt over Victoria’s legislated targets of achieving 2 gigawatts of offshore wind power by 2032 and 4 gigawatts by 2035—milestones critical to meeting its 95% renewables goal and offsetting the planned closures of the Yallourn and Loy Yang A coal generators over the next decade.
Industry bottlenecks, including bureaucratic red tape and ongoing uncertainty surrounding the government's new Electricity Entry Services Mechanism underwriting scheme, have repeatedly stalled progress.
A crucial taxpayer funding auction was pushed back to August, with federal and state negotiations expected to delay tender outcomes until 2027.
Additionally, supply chain pressures persist after Commonwealth regulators previously rejected environmental approvals for a dedicated port facility in Hastings.
Despite the setback, Star of the South CEO Charles Rattray maintained the timeline reflects a maximum duration, noting the project aims to deliver "first power" by 2032.
While Energy Minister Lily D’Ambrosio insists the state remains on track, the extended timeline intensifies pressure on Victoria's grid, which is already grappling with local opposition to onshore infrastructure and skyrocketing electricity demand from a booming data centre sector.