  • Delta Lithium (ASX:DLI) released a Scoping Study for its Mt Ida Lithium Project, estimating a post-tax net present value of A$748 million and a 33% internal rate of return.
  • The project would cost an estimated A$483 million to build, and Delta Lithium shares closed at A$0.14.
  • Delta plans drilling and feasibility work towards a maiden Ore Reserve, and said further funding will likely be required.

Delta Lithium (ASX:DLI) has released a Scoping Study for its Mt Ida Lithium Project in Western Australia, estimating a post-tax net present value of A$748 million and an internal rate of return of 33%, at an accuracy of ±40%.

The study assumes a 1 Mtpa concentrator producing spodumene, lepidolite and tantalum concentrates over an 11-year mine life, with pre-production capital of A$483 million including contingency.

“The Scoping Study demonstrates that Mt Ida has real potential to be a highly profitable and long-life lithium mine,” said Delta Lithium Managing Director James Croser.

Delta estimated post-tax free cash flow of A$1.415 billion and a payback period of 4.3 years, with 27% of the production target drawn from Inferred Resources, which carry lower geological confidence.

The company said further funding will likely be required and may be dilutive to existing shareholders, and it plans drilling and feasibility work towards a maiden Ore Reserve; following the announcement the Delta Lithium share price closed at A$0.14.

Delta said the lepidolite concentrate would earn a rubidium credit, which it valued at 5% payability of the current rubidium carbonate price, citing rubidium’s status as a critical mineral in most Western countries.

The project, about 100 km northwest of Menzies, is fully permitted for open pit and underground mining, and Delta held A$48.8 million in cash at 30 September 2026.