Boss Energy (ASX:BOE) has reported that significant rainfall in South Australia has disrupted operations at its flagship Honeymoon Uranium Project.
The heavy downpours have caused road closures and restricted site access, preventing the delivery of essential reagents and goods required for uranium production.
While the weather has paused active processing, the company is utilising the downtime to conduct a planned shutdown to integrate new plant infrastructure, wellfields, and power systems designed to boost future capacity.
Management expects deliveries and production to resume by March 14, contingent on improving weather and road conditions.
Production forecasts for the third quarter of FY26 have been downgraded to between 240,000 lbs and 270,000 lbs of drummed U3O8.