Theta Gold Mines targets first gold pour in 2027
Pontos principais
- Theta Gold Mines reported that construction of its South African gold processing plant is 81% complete ahead of a planned early 2027 production start.
- The company holds $96.2 million in cash after drawing $109.6 million from its bond facility.
- Theta Gold plans to process existing rock dumps first before transitioning into a 13.1-year underground mining operation.
Theta Gold Mines (ASX:TGM) announced that construction of its Transvaal Gold Mining Estates gold processing plant in South Africa is 81% complete as it targets its first gold pour in the March quarter of 2027.
This progress follows $84.8 million in development spending through October and the stockpiling of 110,000 tonnes of ore for plant commissioning.
The company holds $96.2 million in cash and $20.8 million in undrawn funds after completing a second drawdown on its $136.4 million Nordic bond facility on Nov. 25.
Following the announcement, the Theta Gold Mines share price was down at $0.17.
Theta Gold stated that dry commissioning is scheduled for the December quarter, with final completion in the March quarter remaining subject to regulatory approvals.
The company holds a 74% stake in the Mpumalanga province project, where a February feasibility study projected 871,000 ounces of gold recovery over a 13.1-year operating life.
Theta Gold plans to begin production using existing surface rock dumps while preparing four underground mines out of 43 historical gold sites across its holdings.