Haranga Resources initiated its Senegal Uranium Project's reverse circulation drilling program, scheduled for completion by early February 2024.
The drilling program, spanning 4,000m to 6,000m, focuses initially on the Saraya deposit to fulfil mineral resource estimate upgrade requirements.
Delays caused by the extended wet season have impacted auger drilling at Diobi and Sanela anomalies, affecting mineralisation orientation for reverse circulation drilling.
The auger drilling program, involving reduced spacings and parallel lines at Diobi, will subsequently move to Sanela, continuing through December with minimal disruptions during the year-end holiday period and extending into March 2024.