Grafa
Lindian Resources' Kangankunde Project on track for 2026 first production
Lindian Resources' Kangankunde Project on track for 2026 first production

Lindian Resources' Kangankunde Project on track for 2026 first production

Share

The Kangankunde Rare Earths Project remains on track for its highly anticipated debut, with construction advancing steadily towards a Q4 2026 first production target.

Lindian Resources (ASX:LIN) confirmed that the project is fully funded following a $100 million institutional placement, ensuring no reliance on external debt as the site transitions into its final development phases.

A critical milestone is set for June, when the first ore is scheduled to arrive at the run-of-mine pad.

The early mining commencement—roughly six months ahead of practical completion—is designed to establish substantial stockpiles to ensure a seamless ramp-up once the plant is operational.

Engineering works are progressing rapidly; civil works for the process plant have commenced, with shaking table base pours already completed and excavation for the SAG mill underway.

Infrastructure development is also keeping pace, with the 23km 33kV electrical overhead line progressing on schedule and final commissioning targeted for September.

The Stage 1 process plant is designed for a nameplate capacity of 20,000 tonnes per annum, positioning the project as a significant future supplier in the rare earths sector.

The site has recorded over 615,000 LTI-free work hours, reflecting a disciplined execution of the ramp-up.

At the time of reporting, Lindian Resources’ share price was $0.077.

Frequently asked questions

Connect with us

Grafa is not a financial advisor. You should seek independent, legal, financial, taxation or other advice that relate to your unique circumstances.

Grafa is not liable for any loss caused, whether due to negligence or otherwise arising from the use of or reliance on the information provided directly or indirectly, by use of this platform.